Road Works Ahead in the Wimbledon Area


Traffic disruption and diversions may occur

Gas Main Work Causing South Wimbledon Traffic Delays For Months
Two major pipeline projects are giving grief to local drivers

Below is a list of forthcoming roadworks in the SW19 area which are likely to cause some local delays - including Grand Drive down to one lane until December:

B279 Grand Drive, Raynes Park
23 July — 10 December
Delays likely Lane closure
Works location: Unknown
Works description: LAY 120M OF 75MM PE, 225M OF 90MM PE, 520M OF 125MM PE, 500M OF 180MM PE, ABANDON 205M OF 4" CI, 770M OF 6" CI, 485M OF 8" CI, TRANSFER 66 SERVICES, MAKE 29 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT
Responsibility for works: SGN
Current status: Planned work about to start
Works reference: XW053W114894639-02916
B281 Durham Road, West Wimbledon
23 July — 04 August
Delays likely Road closure
Works location: Unknown
Works description: Sewer repairs in carriageway due to hard blockage in line
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU026002251LSJH--0002

A219 Hartfield Road

04 August — 07 August

Delays likely Lane closure

Works description: d 28 day c /way breaking out and sunk old trench ,break out and reinstate area

Responsibility for works: Merton

Current status: Planned work about to start

Works reference: HC011-352975-1

A238 Coombe Lane, Raynes Park

02 August — 05 August

Delays likely Lane closure

Works description: New water connection 1x63mm B/P UNMTRD supply off of 7" CI main excavating 4m in Footway Our intention is to complete the PermanentReinstatement in the same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU309000803641250040-001

A238,B235 Worple Road, Raynes Park

01 August — 02 August

Delays likely Traffic control (multi-way signals)

Works description: Replace Sewer Cover--WORKS INTENDED TO INCLUDE FIRST TIME PERMANENT REINSTATEMENT WITHIN SAME PHASE

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU026002251VZND--000008

B281 Copse Hill, West Wimbledon

01 August — 04 August

Delays likely Traffic control (multi-way signals)

Works description: Install 13m of 1 way poly duct in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500262818503

B281 Woodhayes Road, West Wimbledon

01 August — 04 August

Delays likely Traffic control (multi-way signals)

Works description: Build 1 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,Demolish 1 existing jointbox(s) or cabinet base(s),Install 25m of 1 way poly duct in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500262818502

Denmark Road, Wimbledon

01 August — 04 August

Delays likely Road closure

Works description: New water connection 1x25mm MDPE MTRD supply off of 4" CI main excavating 2m carriagway and 2m footway

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU309000806530880045-001

 