Planned Roadworks In And Around Wimbledon


Where to watch out for road delays in and around SW19

South Wimbledon roadworks

Current roadworks in the Wimbledon area include:

Queen's Road, Wimbledon

31 August — 12 October 

Severe delays likely - Road closure 

Works location: C/W / F/W- Opposite Quadrangle Lodge to Next to Bus Stop O/S the Police Station 15-23 

Works description: Lay 141mtrs of 125mmPE. Abandon 141mtrs of 6"CI. Complete all services. Complete all connections. Complete all reinstatement. 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW053W116890673-05247

 

Ethelbert Road, Raynes Park

31 August — 07 September 

Delays possible - Traffic control (priority working) 

Works location: 4 

Works description: Lead Serv Pipe Relay Sz P Cway & Fway in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU302000031490939-001 

 

Lauriston Road, Wimbledon

31 August — 03 September 

Delays possible - Some carriageway incursion 

Works location: 10 

Works description: Service Pipe Repair <33mm Cway & Fway in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU302000031496671-001

 

The Broadway, London

29 August — 03 September 

Delays possible - Some carriageway incursion 

Works location: O/S UNIT 1 PRINTERS YARD 90 A THE BROADWAY 

Works description: LAY 2.5M C/W TRACK 

Responsibility for works: VIRGIN MEDIA 

Current status: Planned work about to start 

Works reference: NK104CIV100352618

Durham Road, West Wimbledon

28 August — 03 September 

Delays possible - Some carriageway incursion 

Works location: Outside 36, SW20 0TW 

Works description: New water connection 3x32mm MDPE MTRD supplies off of 3" CI main excavating 1m footway 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU309000809174500160-001

 

Hartfield Road

28 August — 01 September 

Delays possible - Traffic control (give & take) 

Works location: opp 17 nr hartfield crescent 

Works description: d 10 day c way breaking out viafix potholes to make safe area. 400 x .400 x2 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00164870971 

 

Kingston Road, Raynes Park

28 August — 02 September 

Delays possible - Traffic control (multi-way signals) 

Works location: OUTSIDE 442 

Works description: CLEARING A BLOCKAGE 

Responsibility for works: Openreach 

Current status: Planned work about to start 

Works reference: BC1170000000000097721L2C 

 

The Broadway, London

29 August — 03 September 

Delays possible - Some carriageway incursion 

Works location: O/S UNIT 1 PRINTERS YARD 90 A THE BROADWAY 

Works description: LAY 2.5M C/W TRACK 

Responsibility for works: VIRGIN MEDIA 

Current status: Planned work about to start 

Works reference: NK104CIV100352618 

 

Worple Road, Wimbledon

29 August — 03 September 

Delays possible - Some carriageway incursion 

Works location: O/S 79 Worple Rd 

Works description: Interim to permanent 

Responsibility for works: VIRGIN MEDIA 

Current status: Advanced planning 

Works reference: NK104CIV100348810

 

Belvedere Avenue, Wimbledon Village

27 August — 31 August 

Delays possible - Traffic control (give & take) 

Works location: outside 19. 

Works description: RS 28day b-out restore pothole in cw 0.5sqm. 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00155055856

 

Dorien Road, Raynes Park

27 August — 02 September 

Delays possible - Traffic control (give & take) 

Works location: Outside the land adjacent to 91, SW20 8EL 

Works description: New water connection 1x4 port B/P MTRD manifold x1 capped off of 100mm DI main excavating 3m footway and 2m carriageway 

Responsibility for works: THAMES WATER 

Current status: Advanced planning 

Works reference: MU309000810323140045-001

 

Graham Road, Wimbledon

27 August — 31 August 

Delays possible - Traffic control (give & take) 

Works location: outside 54 

Works description: d 28 day c way breaking out, break out and reinstate area 1.8 x .600 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00141958572

Russell Road, Wimbledon

18 August — 12 December 

Severe delays likely - Road closure 

Works location: o/s 13 to o/s 58A 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00245249629

  

The Broadway

17 August — 18 December 

Delays possible - Some carriageway incursion 

Works location: junction Russell Road 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00208199772 

 

Copse Hill, West Wimbledon

03 August — 25 September 

Delays possible - Traffic control (give & take) 

Works location: Footway reconstruction works one side at a time 

Works description: Footway reconstruction works one side at a time 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC0025567494

 

Cranford Close, West Wimbledon

27 July — 01 September 

Delays possible - Traffic control (multi-way signals) 

Works location: WHOLE ROAD, CW & FW 

Works description: GAS MAIN REPLACEMENT. TO LAY 95M OF 75MM PE LP MAIN, RELAY 33 SERVICES, MAKE 1 CONNECTION AND ABANDON EXISTING 4" SI MAIN. COMPLETE REINSTATEMENT. 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW053W117053400-01674 

Russell Road, Wimbledon

20 July — 30 October 

Severe delays likely - Road closure 

Works location: o/s 13 to o/s 58A 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00245249629

 

The Broadway, London, Merton

20 July — 30 October 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: traffic scheme footway upgrade paving  kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011463552   

Wimbledon Bridge, Wimbledon, London, Merton

15 June — 18 November 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary widening of the footway 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011-565935-1

 

Worple Road, Wimbledon, London, Merton

15 June — 22 December 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary footway widening and build out

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HG011-568756-1

August 29, 2020