Current roadworks in the Wimbledon area include:

Bushey Road, Raynes Park

19 August — 20 August 

Delays likely - Lane closure 

Works location: Side Of 27A Gore Road SW20 0JT 

Works description: We need to carry out our essential works by excavating in the F/W to uncover and overhaul leaking critical trunk main valve, back fill and reinstate on day 2 of permit 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU277MV6950658

 

Approach Road, Raynes Park

20 August — 24 August 

Delays possible - Some carriageway incursion 

Works location: 57 

Works description: SEW DESCALE EMERGENCY/REACTIVE 

Responsibility for works: Thames Water 

Current status: Planned work about to start 

Works reference: MU026002252NBXB--000001 

 

Church Road, Wimbledon Village

21 August — 25 August 

Delays possible - Traffic control (give & take) 

Works location: Opposite 68 

Works description: Permanent disconnection 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00400001747 

 

Copse Hill, West Wimbledon

21 August — 27 August 

Delays possible - Some carriageway incursion 

Works location: OPP 92 SW20 0NE 

Works description: Connections Small Service: Disconnection / reconnection of existing electricity supply for a customer: 1 X 3 PHASE DISCONNECTION OF EXISTING SUPPLY 

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON 

Current status: Planned work about to start 

Works reference: EC40089102587 

 

Dorien Road, Raynes Park

19 August — 21 August 

Delays possible - Some carriageway incursion 

Works location: OUTSIDE 22

Works description: Rectify self defect in the Carriageway 

Responsibility for works: Thames Water 

Current status: Planned work about to start 

Works reference: MU302000031457377-003 

 

Gladstone Road, Wimbledon

21 August — 25 August 

Delays possible - Some carriageway incursion 

Works location: Outside number 167 

Works description: New Service ANPR Pole 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00400001723 

 

Kingston Road, Wimbledon

21 August — 25 August 

Delays possible - Some carriageway incursion 

Works location: Outside 140 

Works description: Transfer of services S013 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00400001722 

 

Leopold Road, Wimbledon Park

21 August — 25 August 

Delays possible - Some carriageway incursion 

Works location: Outside 37 JW Leopold Avenue 

Works description: Transfer of services LC010 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00400001726 

 

Palmerston Road, Wimbledon

20 August — 20 August 

Delays possible - Some carriageway incursion 

Works location: Outside 84 

Works description: Install new lamp column. 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00400001714 

 

Worple Road, Raynes Park

20 August — 21 August 

Delays possible - Traffic control (two-way signals) 

Works location: O/S 138, 6M E OF ALBERT GROVE 

Works description: Replacement of old bus shelter with new 3-bay shelter, back of path. TfL shelter ref 0124/8586 (2965233) 

Responsibility for works: Transport for London 

Current status: Planned work about to start 

Works reference: YG471-0124-8586

Russell Road, Wimbledon

18 August — 12 December 

Severe delays likely - Road closure 

Works location: o/s 13 to o/s 58A 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00245249629

 

Copse Hill, West Wimbledon

18 August — 24 August 

Delays possible - Traffic control (two-way signals) 

Works location: os 110 in fway and cway 

Works description: Lay new service to 110 in nearside carriageway and footway under 2 way lights and maintaining 1m for pedestrians 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW047W117310590-01623 

 

Copse Hill, West Wimbledon

19 August — 25 August 

Delays possible - Traffic control (two-way signals) 

Works location: In the public footway O/S 110 Copse Hill. 

Works description: Connections Small Service: Installation of a new electricity supply for a customer: Installation of a new three-phase supply. Works to take place in the public footway. Temp walkway and Two way lights required for duration of works. 

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON 

Current status: Planned work about to start 

Works reference: EC40086788066 

 

Southdown Road, Raynes Park

17 August — 24 August 

Delays possible - Traffic control (give & take) 

Works location: Fway & Cway OS & Opp 72 

Works description: Lay New Service in 2 Phases. PH1, Excavate NS footway maintaining 1.2m for pedestrian access. Excavate NS Carriageway using Give & Take, reinstatement to be carried out before start of 2nd Phase. PH2, Excavate FS Footway maintaining 1.2m for pedestrian access. Excavate FS Carriageway using Give & Take (Possible extra curing time if concrete found) - Parking bay suspension OS 31,35,37,39,68,70,72,74. NPC to be set out night before OS 35,37,39, 70,72,74 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW047W117257350-05901

 

The Broadway

17 August — 18 December 

Delays possible - Some carriageway incursion 

Works location: junction Russell Road 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC00208199772 

 

Windy Ridge Close, Wimbledon

17 August — 21 August 

Delays possible - Traffic control (priority working) 

Works location: 1 x JNT holes. 1 O/S 2 Windy Ridge & the 2nd O/S 4 Windy Ridge. 

Works description: Connections Small Service: Installation of a new electricity supply for a customer: Installation of a new 3phase and disconnection of 1ph. Works in Footway. Temp walkway and priority working for duration of works. 

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON 

Current status: Planned work about to start 

Works reference: EC40094116922 

 

Copse Hill, West Wimbledon

03 August — 25 September 

Delays possible - Traffic control (give & take) 

Works location: Footway reconstruction works one side at a time 

Works description: Footway reconstruction works one side at a time 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC0025567494

 

Cranford Close, West Wimbledon

27 July — 01 September 

Delays possible - Traffic control (multi-way signals) 

Works location: WHOLE ROAD, CW & FW 

Works description: GAS MAIN REPLACEMENT. TO LAY 95M OF 75MM PE LP MAIN, RELAY 33 SERVICES, MAKE 1 CONNECTION AND ABANDON EXISTING 4" SI MAIN. COMPLETE REINSTATEMENT. 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW053W117053400-01674 

Russell Road, Wimbledon

20 July — 30 October 

Severe delays likely - Road closure 

Works location: o/s 13 to o/s 58A 

Works description: traffic scheme footway upgrade paving kerbing with raised table 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00245249629

 

The Broadway, London, Merton

20 July — 30 October 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: traffic scheme footway upgrade paving  kerbing with raised table 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011463552   

Wimbledon Bridge, Wimbledon, London, Merton

15 June — 18 November 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary widening of the footway 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011-565935-1

 

Worple Road, Wimbledon, London, Merton

15 June — 22 December 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary footway widening and build out

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HG011-568756-1

August 19, 2020