Planned Roadworks In And Around Wimbledon


Where else to watch out for road delays in and around SW19

South Wimbledon roadworks

Current roadworks in the Wimbledon area include:

Wimbledon Bridge, Wimbledon, London, Merton

15 June — 18 November 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary widening of the footway 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011-565935-1

 

Worple Road, Wimbledon, London, Merton

15 June — 22 December 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: COVID-19 Temporary Safety Measures. Temporary footway widening and build out 

Responsibility for works: Merton 

Current status: Planned work about to start 

Works reference: HC011-568756-1

Arthur Road, Wimbledon

09 July — 13 July 

Delays possible - Some carriageway incursion 

Works location: by roundabout at jw St Mary's Rd. 

Works description: RS 10day re-bed bollard. B-out restore bitmac fw 1sqm.  

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00125656073 

 

Bernard Gardens, Wimbledon

08 July — 10 July 

Delays possible - Traffic control (give & take) 

Works location: j/w Woodside Wimbledon, London 

Works description: Collapsed pipework at Bernard Gardens junction with Woodside 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00197333849  

 

Coombe Lane, Raynes Park

08 July — 10 July 

Delays possible - Some carriageway incursion 

Works location: outside 108 (Korean Community Centre) 

Works description: RS 28day b-out restore concrete fillet to BT cover 2.1m x100mm. 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00119919259  

 

West Side Common, Wimbledon

10 July — 15 July 

Delays possible - Some carriageway incursion 

Works location: Outside 22 West Side Common, SW19 4UF 

Works description: New water connection, 1x32mm MDPE MTRD supply off of 7" CI main excavating 1m footway 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU309000810177680045-001  

 

Wimbledon Hill Road, Wimbledon

09 July — 13 July 

Delays possible - Some carriageway incursion 

Works location: outside Leon, Unit 1&2, 1-9 Wimbledon Hill Rd. 

Works description: RS 03/07/20 10day level sunken ASP slab on inset cover. 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Advanced planning 

Works reference: HC00197357830

 

Crescent Road, Raynes Park

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: outside 14. 

Works description: RS 28day re-lay raised 750mm ASP slab. B-out restore surrounding bitmac fille 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00109835904 

 

Wimbledon Hill Road, Wimbledon

09 July — 13 July 

Delays possible - Some carriageway incursion 

Works location: outside 19 (Argos). 

Works description: RS 10day re-lay raised paving slabs by kerb 1.4m x1m. Ensure the mortar joints 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Advanced planning 

Works reference: HC00166220917 

 

Worple Road, Wimbledon

08 July — 10 July 

Delays possible - Traffic control (give & take) 

Works location: O/S 79 Worple Road, Wimbledon 

Works description: Clear blockage in carriageway 

Responsibility for works: VIRGIN MEDIA 

Current status: Planned work about to start 

Works reference: NK104CIV100346878

 

Dorien Road, Raynes Park

07 July — 09 July 

Delays possible - Traffic control (priority working) 

Works location: OUTSIDE 22 

Works description: Service Pipe Repair <33mm Cway in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU302000031457377-003  

 

Sherwood Road, Wimbledon

07 July — 09 July 

Delays possible - Traffic control (give & take) 

Works location: OUTSIDE 9 

Works description: Service Pipe Repair <33mm Cway in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU302000031474622-002

 

Worple Road, Raynes Park

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: outside 207 & 209. 

Works description: RS 28day re-lay 2 x rocking 600mm ASP slabs. 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00191534104

 

Worple Road, Wimbledon

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: east side of jw Raymond Rd next to CATV cover. 

Works description: RS 28day re-lay hiload fw 1sqm. B-out restore concrete fillet to CATV cover 1m 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00137752338 

 

Worple Road, Wimbledon

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: outside 2 The Pavement & 28 Wimbledon Hill Rd. 

Works description: RS 28day re-lay hiload fw 1.6m x0.8m plus 1 separate slab. B-out restore conc 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00145074717 

 

Worple Road, Wimbledon

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: opposite 19 at base of lc 005. 

Works description: RS 28day b-out restore concrete fillet to BT cover 1m x100mm. 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00192336377  

 

Worple Road, Wimbledon

07 July — 09 July 

Delays possible - Some carriageway incursion 

Works location: outside 20-22. 

Works description: RS 28day re-lay 1 hiload brick by x-over to Sainsbury's car park. B-out restor 

Responsibility for works: LONDON BOROUGH OF MERTON 

Current status: Planned work about to start 

Works reference: HC00199838211  

 

Worple Road, Wimbledon

08 July — 10 July 

Delays possible - Traffic control (give & take) 

Works location: O/S 79 Worple Road, Wimbledon 

Works description: Clear blockage in carriageway 

Responsibility for works: VIRGIN MEDIA 

Current status: Planned work about to start 

Works reference: NK104CIV100346878

 

Kingston Road, Raynes Park, London, Merton

06 July — 12 July 

Delays possible - Some carriageway incursion 

Works location: Unknown 

Works description: Network Operations Distribution:Install / Replace / Remove electrical link box:Linkbox replacement scheme. Excavation works in the f/w to allow for replacement of linkbox 990457 and associated jointing works. 

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON 

Current status: Planned work about to start 

Works reference: EC40010783117  

 

The Downs, West Wimbledon, London, Merton

06 July — 12 July 

Delays possible - Lane closure 

Works location: Unknown 

Works description: Network Operations Distribution:Install / Replace / Remove ground mounted switchgear / transformers:Disconnect and remove equipment from sub-stn 06383 after excavating a LV cable trench, laying of a duct and cable, excavation of 2No joint holes and HV/LV jointing thereof. 

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON 

Current status: Planned work about to start 

Works reference: EC40010781667

July 8, 2020