Gas Main Project At Key Wimbledon Junction Still Causing Delays


Check where more roadworks are on their way in and around Wimbledon

South Wimbledon roadworks

Gas network bosses are considering longer working times at a major South Wimbledon project after road closures have been causing significant delays to drivers and bus passengers.

The junction at Kingston and Merton Road outside South Wimbledon tube (pictured above) is set to be closed until April 12 while essential Southern Gas Network work is carried out.

The £417,000 project involves replacing old metal gas mains with a new plastic pipe, which will have an 80-year lifespan. Details about the project are on this link.

SGN staff have been working from 8am to 6pm on weekdays, so they do not cause too much disturbance to residents. But since the reports of traffic gridlock near the diversion route in Pelham Road, journeys of a few minutes taking more than an hour and buses not taking the agreed diversion, they were seen working on Saturday (January 25).

SGN have been asked to consider working longer hours - eg on Sundays and until 10pm each night, in order to speed up the completion of the project. South Wimbledon Councillor Nigel Benbow has put this to SGN and they are "looking into it", although a number of Twitter users have pointed out there are many daylight hours when there are no workers on site.

Councillor Benbow and Wimbledon MP Stephen Hammond have already met with SGN representatives on the site.

Councillor Benbow said on Twitter: “I have already spoken to a number of workmen there on different occasions and queried why they are sometimes not seen. There are some certain jobs they can do and would require gas pipe specialists to do the main pipelines.”

Since the traffic problems developed, Merton Council has improved the signage, with details below. But buses have still been seen being driven off the diversion route.

There are many other roadworks in the SW19 area which are likely to cause some local delays, including the 12-week road closure at South Wimbledon. They are all detailed below:

A238 Kingston Road, Wimbledon

20 January - 12 April

Responsibility for these works

SGN

 

Information for Road Users

Location:

A238 Kingston Road, Wimbledon

Traffic lights, etc:

Traffic control (multi-way signals)

Gas network upgrade

We’re upgrading our network to ensure local homes and businesses continue to enjoy a safe and reliable gas supply for years to come.
Our project will start on Monday 13 January and last approximately 12 weeks. It will involve road and lane closures around our site to keep everyone safe. 

A238 Pepys Road, Raynes Park

20 January — 17 February

Delays likely - Lane closure

Works location: Unknown

Works description: 12 mtrs of 180mm road crossing (new lay) 37mtrs of 75mm in 8". Cut off 10" main from 15mm. Abandon 20mtrs of 10/8" mains. Complete all services. Complete all reinstatement.

Responsibility for works: SGN

Current status: Planned work about to start

Works reference: XW053W116378314-05055

Wyke Road, Raynes Park, London, Merton

14 February — 12 March 

Delays likely - Road closure 

Works location: Unknown 

Works description: Road Closure, to assist with Pepys Road project 

Responsibility for works: SGN 

Current status: Planned work about to start 

Works reference: XW053W116994565-06909

 

A238 Kingston Road, Wimbledon, London, Merton

12 February — 14 February 

Delays likely - Contra-flow 

Works location: Unknown 

Works description: Install 3m of 1 way poly duct in Footway 

Responsibility for works: Openreach 

Current status: Planned work about to start 

Works reference: BC006TI001LC500292849500

 

Calonne Road, Wimbledon Park, London, Merton

10 February — 07 April

 

Delays possible - Traffic control (multi-way signals) 

Works location: Unknown 

Works description: WORKING ON BEHALF OF THAMES WATER - MAINS RENEWAL - 530M OF INSERTION - 40 SERVICES & 3 MAINS CONNECTIONS 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU821H577/MMWIMBC08/D002

 

Parkside Gardens, Wimbledon, London, Merton

10 February — 07 April 

Delays possible - Traffic control (multi-way signals) 

Works location: Unknown 

Works description: WORKING ON BEHALF OF THAMES WATER - MAINS RENEWAL - 514M OF DIRECTIONAL DRILLING 

Responsibility for works: THAMES WATER 

Current status: Planned work about to start 

Works reference: MU821H577/MMWIMBC08/D003

 

February 13, 2020