Road Works Ahead in the Wimbledon Area


Traffic disruption and diversions may occur

Kingston Road roadworks

Gas Main Work Causing South Wimbledon Traffic Delays For Months
Two major pipeline projects are giving grief to local drivers.

Below is a list of forthcoming roadworks in the SW19 area which are likely to cause some local delays - including Grand Drive down to one lane until December:

A238 Coombe Lane, Raynes Park, London, Merton
23 August — 24 August
Delays likely Traffic control (two-way signals)
Works location: Unknown
Works description: Council Defect to apply anti-skid
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU309000805102340045-001
A219 Wimbledon Hill Road, Wimbledon, London, Merton
22 August — 24 August
Delays likely Lane closure
Works location: Unknown
Works description: Non excavation - MEWP to be placed in road to work on the the Hand & racquet installing telecommunications equipment.
Responsibility for works: O2 (UK) Limited
Current status: Planned work about to start
Works reference: MG0857277-PGN/ERF
A238 Kingston Road, Raynes Park, London, Merton
21 August — 24 August
Delays likely Traffic control (two-way signals)
Works location: Unknown
Works description: Serv Pipe Relay Inc Fitting Sz P within Carriagway andFootway only. Our intention is to complete the Permanent Reinstatementin thesame phase
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU302000031049947-001
B281 Copse Hill, West Wimbledon, London, Merton
21 August — 24 August
Delays likely Traffic control (Stop/Go boards)
Works location: Unknown
Works description: RVS 28day supply 2 x 1m granite radius kerbs. HRA cw channel repair 2sqm.
Responsibility for works: Merton
Current status: Planned work about to start
Works reference: HC011-345973-1A
B279 Grand Drive, Raynes Park
23 July — 10 December
Delays likely Lane closure
Works description: LAY 120M OF 75MM PE, 225M OF 90MM PE, 520M OF 125MM PE, 500M OF 180MM PE, ABANDON 205M OF 4" CI, 770M OF 6" CI, 485M OF 8" CI, TRANSFER 66 SERVICES, MAKE 29 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT
Responsibility for works: SGN
Current status: Planned work about to start
Works reference: XW053W114894639-02916

Church Hill, Wimbledon Park

06 August — 15 September

Delays likely Road closure

Works description: To carry out works on speed table at the junction

Responsibility for works: Merton

Current status: Advanced planning

Works reference: HC011306208

Church Hill, Wimbledon Park

06 August — 15 September

Delays likely Road closure

Works description: To carry out works on speed table at the junction

Responsibility for works: Merton

Current status: Advanced planning

Works reference: HC011306316

Church Hill, Wimbledon Park

06 August — 15 September

Delays likely Road closure

Works description: To carry out works on speed table at the junction

Responsibility for works: Merton

Current status: Planned work about to start

Works reference: HC011306360

 

 

August 23, 2018