Road Works Ahead in the Wimbledon Area


Traffic disruption and diversions may occur

Below is a list of forthcoming roadworks in the SW19 area which are likely to cause some local delays:

A298 Bushey Road, Raynes Park, London, Merton
21 August — 25 August
Delays likely Road closure
Works location: A298
Works description: Lay Anti Skid To The Approache To The Crossing Point
Responsibility for works: Merton London Borough Council
Current status: Work in progress
A298 Bushey Road, Raynes Park, London, Merton
21 August — 25 August
Delays likely Road closure
Works location: A298
Works description: Lay Anti Skid To The Approache To The Crossing Point
Responsibility for works: Merton London Borough Council
Current status: Work in progress
B235 St George'S Road, London, Merton
20 August — 21 August
Delays likely Lane closure
Works location: B235
Works description: Drainage Repairs In Carriageway
Responsibility for works: Merton London Borough Council
Current status: Planned work about to start
A219 The Broadway, London, Merton
14 August — 25 August
Delays likely Traffic control (two-way signals)
Works location: A219
Works description: Sewer Failure--Works Intended To Include First Time Permanent Reinstatement Within Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
Southey Road, Wimbledon, London, Merton
14 August — 25 August
Delays likely Road closure
Works location: -
Works description: -
Responsibility for works: Thames Water
Current status: Planned work about to start
 