Road Works Ahead in the Wimbledon Area
Traffic disruption and diversions may occur
Below is a list of forthcoming roadworks in the SW19 area which are likely to cause some local delays.
| A238/A24 High Street Collier's Wood, Colliers Wood, London, Merton |
| 12 May — 15 May |
| Delays likely Traffic control (two-way signals) |
| Works location: A238/A24 |
| Works description: Chamber Adjust Lrg Frame& Cover Cway In Carriageway. Ourintention Is To Complete The Permanent Reinstatement In The Same Phase |
| Responsibility for works: Thames Water |
| Current status: Planned work about to start |
| A238/A24 High Street Collier's Wood, Colliers Wood, London, Merton |
| 12 May — 15 May |
| Delays likely Traffic control (two-way signals) |
| Works location: A238/A24 |
| Works description: Chamber Adjust Lrg Frame& Cover Cway In Carriageway. Ourintention Is To Complete The Permanent Reinstatement In The Same Phase |
| Responsibility for works: Thames Water |
| Current status: Planned work about to start |
| A3 Beverley Way, West Wimbledon, London, Merton |
| 12 May — 17 May |
| Delays likely Lane closure |
| Works location: Southbound, From Beverey Way (Kingston) Heading South To Shannon Corner Junction |
| Works description: Tarmac Patches And Barrier Repairs Lane 1 And 2 With Switches To 2 And 3 Where Required |
| Responsibility for works: Transport For London |
| Current status: Planned work about to start |
| A218 Haydon'S Road, South Wimbledon, London, Merton |
| 12 May — 16 May |
| Delays possible |
| Works location: A218 |
| Works description: Connections Small Service:Service Upgrade: (Approx Depth 450mm):Excavate And Expose Mains Cable For The Installation Of 100amp Service And Removal Of An Existing Supply. |
| Responsibility for works: UK Power Networks |
| Current status: Planned work about to start |
| A219 Merton Road, South Wimbledon, London, Merton |
| 13 May — 15 May |
| Delays possible |
| Works location: A219 |
| Works description: Service Pipe Repair In The Fway In Footway. Our Intention Is To Completethe Permanent Reinstatement In The Same Phase |
| Responsibility for works: Thames Water |
| Current status: Planned work about to start |
| A219 Wimbledon Hill Road, Wimbledon, London, Merton |
| 13 May — 16 May |
| Delays possible |
| Works location: A219 |
| Works description: Connections Highway Services:Disconnection: (Approx Depth 450mm):Disconnection Of Electrical Supply To A Bus Shelter |
| Responsibility for works: UK Power Networks |
| Current status: Planned work about to start |
| A219 Wimbledon Park Side, Southfields, London, Wandsworth |
| 13 May — 13 May |
| Delays possible |
| Works location: A219 |
| Works description: Remedial Works To Be Carried Out - Replace Buff Anti Skid - Pedestrian Crossing Closed |
| Responsibility for works: Southern Gas Networks Plc |
| Current status: Planned work about to start |
| A238 Kingston Road, Wimbledon, London, Merton |
| 13 May — 15 May |
| Delays possible |
| Works location: A238 |
| Works description: Service Pipe Repair In The Fway And Cway In Carriageway. Our Intention is To Complete The Permanent Reinstatement In The Same Phase |
| Responsibility for works: Thames Water |
| Current status: Planned work about to start |